Al-Ubayyah
22 Sept 2026

22 Sept 2026

88%Overall▲ +7% · vs previous visit

Main video

Engineering Report

Significant progress has been made in finishing and electrical works since the previous visit, with the project's overall completion reaching 88%. Current efforts are focused on final interior finishes and the installation of electrical and mechanical systems.
Detected changes
Finishing Works95%

Completion of interior painting, window installation, and sanitary ware fitting, with ongoing final finishing works in interior spaces.

Electrical and Plumbing Works90%

Progress in cable routing and installation of cable trays in suspended ceilings, in addition to the completion of plumbing installations within the units.

Exterior Facades85%

The facade is largely complete, with scaffolding remaining in some sections, indicating ongoing final touches or cleaning.

Progress reading

The images reflect a 15% increase in finishing works and a 10% increase in electrical works, which aligns with visual observations of window installations, painting, and ceiling wiring, placing the project in an advanced stage toward delivery.

vs previous visit

Compared to the previous visit, the project has progressed from the foundation and initial finishing stage to the final finishing stage, including the installation of plumbing and electrical fixtures, with a clear improvement in both the exterior and interior appearance of the building.

Expected next milestones

Completion of lighting installation, finishing of suspended ceilings, and final site cleaning in preparation for handover.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +6%
Concrete Works
0%
Plumbing Works
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +15%
0%