22 Sept 2026
Main video
Engineering Report
Detected changes
Completion of the concrete structure and exterior facades, including window installation and final facade finishes.
Installation of sanitary ware, wall painting, and room preparation, with some construction debris remaining in certain areas.
Installation of cable trays and piping in suspended ceilings, with primary installations now complete.
Progress reading
The images reflect substantial progress in finishing works (a 25% increase) and electrical systems (a 21% increase). Interior photos show the completion of wiring and primary finishes, while exterior photos demonstrate that the facades are nearly finalized.
vs previous visit
Compared to the previous visit, the project has progressed from the structural and initial finishing phase to the final touches and systems installation phase, with the previously visible external scaffolding now removed.
Expected next milestones
Final site cleaning, electromechanical systems testing, and project handover.