Al Obaya Residence
22 Sept 2026

22 Sept 2026

95%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The project has seen significant progress in finishing works and electromechanical systems, with the overall completion rate reaching 95%. Exterior facade works and window installations are complete, while final interior fit-out works are ongoing.
Detected changes
Concrete Structure and Facades100%

Completion of the concrete structure and exterior facades, including window installation and final facade finishes.

Interior Finishing Works95%

Installation of sanitary ware, wall painting, and room preparation, with some construction debris remaining in certain areas.

Electrical and Plumbing Works92%

Installation of cable trays and piping in suspended ceilings, with primary installations now complete.

Progress reading

The images reflect substantial progress in finishing works (a 25% increase) and electrical systems (a 21% increase). Interior photos show the completion of wiring and primary finishes, while exterior photos demonstrate that the facades are nearly finalized.

vs previous visit

Compared to the previous visit, the project has progressed from the structural and initial finishing phase to the final touches and systems installation phase, with the previously visible external scaffolding now removed.

Expected next milestones

Final site cleaning, electromechanical systems testing, and project handover.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +13%
Concrete Works
0%
Plumbing Works▲ +7%
0%
Electrical Works▲ +21%
0%
Finishing Works▲ +25%
0%

Drone Photography

Ground Photography

360° View

3D Rendering