22 Sept 2026
Main video
Engineering Report
Detected changes
Completion of interior painting, window installation, and sanitary ware fitting, with ongoing final finishing works in interior spaces.
Progress in cable routing and installation of cable trays in suspended ceilings, in addition to the completion of plumbing installations within the units.
The facade is largely complete, with scaffolding remaining in some sections, indicating ongoing final touches or cleaning.
Progress reading
The images reflect a 15% increase in finishing works and a 10% increase in electrical works, which aligns with visual observations of window installations, painting, and ceiling wiring, placing the project in an advanced stage toward delivery.
vs previous visit
Compared to the previous visit, the project has progressed from the foundation and initial finishing stage to the final finishing stage, including the installation of plumbing and electrical fixtures, with a clear improvement in both the exterior and interior appearance of the building.
Expected next milestones
Completion of lighting installation, finishing of suspended ceilings, and final site cleaning in preparation for handover.