10 Jul 2025
Main video
Engineering Report
Detected changes
Installation of outdoor AC units and completion of waterproofing and thermal insulation across extensive sections.
Completion of pool filling, installation of stone flooring, and artificial landscaping.
Completion of exterior painting and finishing works for most buildings surrounding the courtyard.
Presence of residual construction materials and ongoing plastering works in some rooftop rooms.
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates that the project has reached the final finishing stages. This discrepancy is due to the fact that this report serves as the baseline.
vs previous visit
No previous visit available for comparison
Expected next milestones
Removal of construction debris from rooftops, completion of wooden pergola installations, and commencement of final inspection and handover procedures.