Al-Ubayyah
10 Jul 2025

10 Jul 2025

95%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Significant progress has been observed in the Al-Ubayyah project, with the concrete structures of the main buildings reaching their final stages. The images show the completion of external facade work for the majority of the blocks, while work continues on roof finishes and open areas. Additionally, the construction of the swimming pool and internal landscaping is largely complete, with some construction materials remaining in specific roof areas.
Detected changes
Rooftops100%

Installation of outdoor AC units and completion of waterproofing and thermal insulation across extensive sections.

Internal Courtyard95%

Completion of pool filling, installation of stone flooring, and artificial landscaping.

External Facades100%

Completion of exterior painting and finishing works for most buildings surrounding the courtyard.

Upper Service Area90%

Presence of residual construction materials and ongoing plastering works in some rooftop rooms.

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates that the project has reached the final finishing stages. This discrepancy is due to the fact that this report serves as the baseline.

vs previous visit

No previous visit available for comparison

Expected next milestones

Removal of construction debris from rooftops, completion of wooden pergola installations, and commencement of final inspection and handover procedures.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%