21 May 2026
Engineering Report
Detected changes
Completion of the building's structural frame, including roof rooms and parapets.
Continuation of external plastering and commencement of the primary painting stages, with safety netting and scaffolding remaining on most facades.
Execution of internal plastering and wall painting (first coat), and installation of aluminum window frames in some openings.
Installation of supply and drainage lines in bathrooms and kitchens, and completion of electrical conduits and wiring in ceilings and walls.
Commencement of insulation and tiling works for the building's roof, with surrounding areas still being used for material storage.
Progress reading
The visual evidence aligns with the reported completion rates; the structural completion (100%) is clearly visible, while interior photos reflect the progress of plumbing (80%) and electrical (60%) works through the visible installations. Finishing works (65%) are evident in the plastering stages, primary painting, and the installation of window frames.
vs previous visit
Compared to the previous visit, there is a tangible 15% progress in plumbing, electrical, and finishing works, as the project has transitioned from the structural shell stage to advanced installations and interior/exterior finishes.
Expected next milestones
Completion of final painting works, installation of sanitary and electrical fixtures, and removal of external scaffolding following the completion of the building facades.