Al-Ubayyah
21 May 2026

21 May 2026

76%Overall▲ +11% · vs previous visit

Engineering Report

The concrete structure has been 100% completed, with significant progress in interior finishing and exterior facades reaching 65%. Plumbing and electrical works are progressing well at 80% and 60% respectively, while external scaffolding remains in place to complete plastering and final painting works.
Detected changes
Concrete Structure100%

Completion of the building's structural frame, including roof rooms and parapets.

Exterior Facades95%

Continuation of external plastering and commencement of the primary painting stages, with safety netting and scaffolding remaining on most facades.

Interior Finishing Works90%

Execution of internal plastering and wall painting (first coat), and installation of aluminum window frames in some openings.

Plumbing and Electrical Works85%

Installation of supply and drainage lines in bathrooms and kitchens, and completion of electrical conduits and wiring in ceilings and walls.

General Site and Roof90%

Commencement of insulation and tiling works for the building's roof, with surrounding areas still being used for material storage.

Progress reading

The visual evidence aligns with the reported completion rates; the structural completion (100%) is clearly visible, while interior photos reflect the progress of plumbing (80%) and electrical (60%) works through the visible installations. Finishing works (65%) are evident in the plastering stages, primary painting, and the installation of window frames.

vs previous visit

Compared to the previous visit, there is a tangible 15% progress in plumbing, electrical, and finishing works, as the project has transitioned from the structural shell stage to advanced installations and interior/exterior finishes.

Expected next milestones

Completion of final painting works, installation of sanitary and electrical fixtures, and removal of external scaffolding following the completion of the building facades.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +11%
Concrete Works
0%
Plumbing Works▲ +15%
0%
Electrical Works▲ +15%
0%
Finishing Works▲ +15%
0%

Drone Photography

Ground Photography

360 View

ShareChat on WhatsApp