Al Obaya Residence
21 May 2026

21 May 2026

76%Overall▲ +11% · vs previous visit

Engineering Report

The concrete structure has been 100% completed, with significant progress in interior finishing and exterior facades reaching 65%. Plumbing and electrical works are progressing well at 80% and 60% respectively, while external scaffolding remains in place to complete plastering and final painting works.
Detected changes
Concrete Structure100%

Completion of the building's structural frame, including roof rooms and parapets.

Exterior Facades

Continuation of external plastering and commencement of the primary painting stages, with safety netting and scaffolding remaining on most facades.

Interior Finishing Works65%

Execution of internal plastering and wall painting (first coat), and installation of aluminum window frames in some openings.

Plumbing and Electrical Works60%

Installation of supply and drainage lines in bathrooms and kitchens, and completion of electrical conduits and wiring in ceilings and walls.

General Site and Roof

Commencement of insulation and tiling works for the building's roof, with surrounding areas still being used for material storage.

Progress reading

The visual evidence aligns with the reported completion rates; the structural completion (100%) is clearly visible, while interior photos reflect the progress of plumbing (80%) and electrical (60%) works through the visible installations. Finishing works (65%) are evident in the plastering stages, primary painting, and the installation of window frames.

vs previous visit

Compared to the previous visit, there is a tangible 15% progress in plumbing, electrical, and finishing works, as the project has transitioned from the structural shell stage to advanced installations and interior/exterior finishes.

Expected next milestones

Completion of final painting works, installation of sanitary and electrical fixtures, and removal of external scaffolding following the completion of the building facades.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +11%
Concrete Works
0%
Plumbing Works▲ +15%
0%
Electrical Works▲ +15%
0%
Finishing Works▲ +15%
0%

Drone Photography

Ground Photography

360° View

3D Model