23 Jul 2026
Main video
Engineering Report
Detected changes
Ongoing external plastering works and installation of aluminum window frames, with scaffolding and safety netting in place.
Execution of wall and ceiling plastering, installation of electrical boxes, and commencement of tiling in some wet areas.
Installation of rooftop water tanks and completion of roof waterproofing, while the general site remains under preparation.
Progress reading
The photos align with the reported completion rates; images (9-19) reflect progress in electrical, plumbing, and interior finishing at rates ranging from 70-85%, while aerial photos confirm that the concrete structure is 100% complete.
vs previous visit
Compared to the previous visit, there is a clear progress in closing most external openings with the installation of window frames, along with significant advancement in interior ceiling plastering and the installation of hanging electrical wiring, which were not as prominently visible before.
Expected next milestones
Completion of window glass installation, commencement of final paint coats, and installation of final sanitary and electrical fixtures.