Al-Ubayyah
23 Jul 2026

23 Jul 2026

81%Overall▲ +5% · vs previous visit

Main video

Engineering Report

The Al-Obaiya project is 81% complete, with the concrete structure fully finished and significant progress made in interior finishing and exterior facades. Current work is focused on window installation, electrical wiring, plastering, and primary painting.
Detected changes
Exterior Facades95%

Ongoing external plastering works and installation of aluminum window frames, with scaffolding and safety netting in place.

Interior Finishing Works90%

Execution of wall and ceiling plastering, installation of electrical boxes, and commencement of tiling in some wet areas.

Roof and General Site95%

Installation of rooftop water tanks and completion of roof waterproofing, while the general site remains under preparation.

Progress reading

The photos align with the reported completion rates; images (9-19) reflect progress in electrical, plumbing, and interior finishing at rates ranging from 70-85%, while aerial photos confirm that the concrete structure is 100% complete.

vs previous visit

Compared to the previous visit, there is a clear progress in closing most external openings with the installation of window frames, along with significant advancement in interior ceiling plastering and the installation of hanging electrical wiring, which were not as prominently visible before.

Expected next milestones

Completion of window glass installation, commencement of final paint coats, and installation of final sanitary and electrical fixtures.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +5%
Concrete Works
0%
Plumbing Works▲ +5%
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +5%
0%