Engineering Report
Detected changes
Installation of glass and marble facade panels is nearly complete, with most external scaffolding removed, clearly revealing the final design.
Installation of upper water tanks and organization of HVAC and mechanical systems on the roof are complete, along with the finishing of insulation and tiling works.
Installation of built-in wooden cabinets, concealed LED lighting units, and interior window and door frames is underway.
Firefighting systems (red piping) and electrical cable trays are visible in the open ceilings of corridors and parking areas.
Leveling of the building's front grounds and entrance preparation has commenced, while some construction materials remain in the setback area.
Progress reading
The 15% increase since the previous visit reflects the transition from the structural and basic facade phase to the fine finishing and internal systems phase, which is consistent with the project reaching 90% completion.
vs previous visit
Compared to photos from the previous visit (such as photos 21 and 26), we observe the completion of the glass openings' sealing on the facades, the clearing of large construction debris from the general site, and the commencement of installing interior aesthetic elements that were not previously present.
Expected next milestones
Completion of external paving works, installation of final sanitary fixtures, and testing and commissioning of fire systems and elevators.