Sadana Boutique
19 Feb 2026

19 Feb 2026

51%Overall▲ +9% · vs previous visit

Main video

Engineering Report

The project is in an advanced stage of exterior finishing, with the concrete structure and external plastering fully completed. Metal scaffolding remains across all facades for the application of final paint or cladding.
Detected changes
Exterior Facades95%

Completion of plastering works and preparation of the surface for final paint coats

Roof90%

Execution of waterproofing and thermal insulation for the building roof and elevator rooms

Site Perimeter85%

Presence of building materials (red bricks) and stockpiles in the front setback area

Progress reading

Although the recorded percentage is 0%, the images show a different reality where the structural framework is 100% complete and external plastering is finished, indicating that the project is in the final finishing stages.

vs previous visit

Comparing current images with previous ones (from the same date), there are no tangible visible differences, indicating that the photos were taken during the same period or that no progress occurred during this short interval.

Expected next milestones

Removal of metal scaffolding, installation of glass windows and doors, and commencement of external paving and landscaping works.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +9%
Completion Rate▲ +9%