Sadana Boutique
19 Feb 2026

19 Feb 2026

42%Overall▲ +17% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in the construction works of the Sadana Boutique project. The work has transitioned from the concrete structure and wooden roof formwork phase seen in the previous visit to an advanced stage of external plastering and the installation of metal scaffolding across all facades.
Detected changes
Structural Framework100%

Completion of the final floor and upper annex roof slab casting, with full removal of wooden formwork.

Exterior Facades95%

Commencement of exterior plastering works and installation of metal scaffolding covering the main and side facades.

Roof100%

Execution of initial waterproofing and thermal insulation works, and installation of concrete parapets around the roof.

General Site85%

Clearing the work area around the building of wood and steel debris, and stockpiling new building materials (red bricks).

Progress reading

The images show the project's transition from the structural skeleton phase (which was evident in August 2025) to the external finishing phase. This indicates a good pace of work, despite the recorded completion rate in the data being 0%, which may not reflect the actual reality shown in the photos.

vs previous visit

Compared to the visit on 2025-08-13, we observe the completion of the concrete pouring for the slabs that were under construction, the removal of all wooden formwork, and the actual commencement of facade cladding, along with the partial closing of architectural openings.

Expected next milestones

Completion of external plastering works, commencement of window metal frame installation, and the start of internal electromechanical (MEP) installations.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +17%
Completion Rate▲ +17%
0%

Drone Photography

360 Video

On-site Photography

3D Rendering