19 Feb 2026
Main video
Engineering Report
Detected changes
Completion of the final floor and upper annex roof slab casting, with full removal of wooden formwork.
Commencement of exterior plastering works and installation of metal scaffolding covering the main and side facades.
Execution of initial waterproofing and thermal insulation works, and installation of concrete parapets around the roof.
Clearing the work area around the building of wood and steel debris, and stockpiling new building materials (red bricks).
Progress reading
The images show the project's transition from the structural skeleton phase (which was evident in August 2025) to the external finishing phase. This indicates a good pace of work, despite the recorded completion rate in the data being 0%, which may not reflect the actual reality shown in the photos.
vs previous visit
Compared to the visit on 2025-08-13, we observe the completion of the concrete pouring for the slabs that were under construction, the removal of all wooden formwork, and the actual commencement of facade cladding, along with the partial closing of architectural openings.
Expected next milestones
Completion of external plastering works, commencement of window metal frame installation, and the start of internal electromechanical (MEP) installations.