13 Aug 2025
Main video
Engineering Report
Detected changes
Completion of reinforcement steel laying and installation of PVC conduits for drainage and electricity
Organization of red brick stockpiles in the front yard in preparation for masonry works
Completion of casting for the top floor columns and commencement of formwork for the roof slab
Progress reading
Although the recorded completion rate is 0%, the images reflect tangible progress in the structural framework that significantly exceeds the skeleton stage, with work having reached the building's final roof.
vs previous visit
Comparing the current visit photos with the previous ones (taken on the same date), the site condition shows stability with full readiness for pouring the final floor roof slab, and the availability of necessary materials (bricks) to begin the next phase.
Expected next milestones
Pouring the concrete for the final floor roof slab, commencing internal and external partition masonry work, and starting plastering and initial installation works.