13 Aug 2025
Main video
Engineering Report
Detected changes
Completion of formwork, reinforcement steel placement, and PVC piping installation in preparation for concrete pouring
Clear demarcation of elevator shafts and lightwell openings in the center of the slab
Delivery and onsite storage of red bricks, with temporary site offices (caravans) present
Completion of concrete pouring for typical floor columns and removal of formwork for some lower sections
Progress reading
Although the recorded overall completion rate is 0% (as per the baseline report), the site photos reflect a different reality, showing that a significant portion of the concrete structure has been completed. Work is currently underway on the reinforcement of the final roof, indicating that the structural shell phase is nearing completion.
vs previous visit
No previous visit available for comparison
Expected next milestones
Pouring the concrete for the upper roof slab, commencing brickwork, and starting the initial mechanical and electrical (MEP) installations.