Sadana Boutique
13 Aug 2025

13 Aug 2025

10%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A site visit to the Sadana Boutique project was conducted on August 13, 2025. The project is currently in an advanced stage of structural concrete work. Efforts are focused on preparing the reinforcement steel and electrical and plumbing installations for the roof of the final floor, with building materials (red bricks) already on-site to commence masonry work.
Detected changes
Structural Framework - Upper Roof95%

Completion of formwork, reinforcement steel placement, and PVC piping installation in preparation for concrete pouring

Service Area and Lightwell90%

Clear demarcation of elevator shafts and lightwell openings in the center of the slab

Site Ground (Courtyard)95%

Delivery and onsite storage of red bricks, with temporary site offices (caravans) present

Columns and Lower Ceilings85%

Completion of concrete pouring for typical floor columns and removal of formwork for some lower sections

Progress reading

Although the recorded overall completion rate is 0% (as per the baseline report), the site photos reflect a different reality, showing that a significant portion of the concrete structure has been completed. Work is currently underway on the reinforcement of the final roof, indicating that the structural shell phase is nearing completion.

vs previous visit

No previous visit available for comparison

Expected next milestones

Pouring the concrete for the upper roof slab, commencing brickwork, and starting the initial mechanical and electrical (MEP) installations.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%