Sadana (2) Complex
30 Aug 2025

30 Aug 2025

43%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The concrete structure of the Sadana (2) complex main building has been completed up to the roof of the final floor, with red and cement brickwork commencing across various levels. The site is currently in an advanced stage of initial construction works.
Detected changes
Concrete Structure95%

Completion of pouring columns and slabs for typical floors up to the roof level, with reinforcement steel ready for the upper annex columns.

Masonry Works (Walls)90%

Execution of red and cement brickwork on the ground, first, and second floors at varying completion rates, with additional brick supplies staged on the slabs.

Site Perimeter85%

Installation of the temporary external hoarding (project advertising panels) and preparation of the service area and temporary offices.

محيط المشروع95%

تركيب السور المؤقت (البرندات) ولوحات المشروع التعريفية في الواجهة الأمامية

Progress reading

Although the officially recorded completion rate is 0%, visual evidence shows significant progress in the structural framework and masonry. This indicates a need to update the bill of quantities and completion percentages to reflect the actual status on the ground.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of roof columns and parapet casting, commencement of initial electrical and plumbing installations, and completion of masonry work for all floors.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%