30 Aug 2025
Main video
Engineering Report
Detected changes
Completion of pouring columns and slabs for typical floors up to the roof level, with reinforcement steel ready for the upper annex columns.
Execution of red and cement brickwork on the ground, first, and second floors at varying completion rates, with additional brick supplies staged on the slabs.
Installation of the temporary external hoarding (project advertising panels) and preparation of the service area and temporary offices.
تركيب السور المؤقت (البرندات) ولوحات المشروع التعريفية في الواجهة الأمامية
Progress reading
Although the officially recorded completion rate is 0%, visual evidence shows significant progress in the structural framework and masonry. This indicates a need to update the bill of quantities and completion percentages to reflect the actual status on the ground.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of roof columns and parapet casting, commencement of initial electrical and plumbing installations, and completion of masonry work for all floors.