16 Dec 2025
Main video
Engineering Report
Detected changes
Completion of column and slab casting for all floors, reaching the upper annex and the roof.
Installation of metal scaffolding and green safety netting on the side facade, with the commencement of plastering or exterior cladding works.
Execution of waterproofing and thermal insulation, and installation of roof tiling across extensive areas, with the central section still in progress.
The general site remains unpaved, currently serving as temporary parking and material storage areas.
Progress reading
Although the recorded completion rate is 0%, visual evidence indicates that the concrete structure is fully complete and the finishing phase has begun. The images show a building consisting of 4 typical floors plus the annex, signifying that the structural shell phase has been surpassed.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of external plastering works, commencement of window and aluminum installation, and start of internal electromechanical piping and wiring works.