9 Oct 2026
Main video
Engineering Report
Detected changes
Completion of reinforcement steel works for the concrete foundation and commencement of phased ready-mix concrete pouring.
Site preparation for receiving pouring equipment and staging of construction materials (reinforcement steel and formwork) in areas adjacent to the pouring zone.
Progress reading
The images reflect a 3% progress in overall completion, which visually aligns with the transition from the excavation and site preparation phase to the main concrete foundation pouring phase.
vs previous visit
Compared to the previous visit, which was limited to excavation and site preparation, the site is now in an advanced construction phase, featuring a complete reinforcement steel grid and active concrete pouring operations.
Expected next milestones
Completion of the entire concrete foundation slab pouring, commencement of ground floor column preparation, and initiation of foundation waterproofing works.