Sadana Elemental
9 Oct 2026

9 Oct 2026

8%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The current site visit shows tangible progress in structural works, with the reinforcement of the concrete raft foundation completed and concrete pouring operations underway using both stationary and mobile pumps on-site.
Detected changes
Concrete Structure100%

Completion of reinforcement steel works for the concrete foundation and commencement of phased ready-mix concrete pouring.

Site Layout90%

Site preparation for receiving pouring equipment and staging of construction materials (reinforcement steel and formwork) in areas adjacent to the pouring zone.

Progress reading

The images reflect a 3% progress in overall completion, which visually aligns with the transition from the excavation and site preparation phase to the main concrete foundation pouring phase.

vs previous visit

Compared to the previous visit, which was limited to excavation and site preparation, the site is now in an advanced construction phase, featuring a complete reinforcement steel grid and active concrete pouring operations.

Expected next milestones

Completion of the entire concrete foundation slab pouring, commencement of ground floor column preparation, and initiation of foundation waterproofing works.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +3%
Completion Rate▲ +3%
0%

Drone Footage

3D Model

ShareChat on WhatsApp