Sadana Elementa
25 Nov 2026

25 Nov 2026

20%Overall▲ +12% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in the concrete structure works, with the ground floor slab casting completed and foundations and columns prepared for the next phases, while reinforcement and formwork continue in other parts of the site.
Detected changes
Completion Percentage

Significant progress on the concrete structure; the roof of the completed area has been cast, and the first-floor columns are prepared, while carpentry and steel reinforcement works continue for the foundations in the remaining areas.

Progress reading

The overall completion rate has increased from 8% to 20% (+12%), which visually aligns with the transition from the foundation stage to the casting of the ground floor slab and the commencement of the first-floor columns.

vs previous visit

Compared to the previous visit, the site has transitioned from excavation and initial foundation work to a completed concrete roof structure, with a noticeable increase in labor and equipment (concrete pumps) on-site.

Expected next milestones

Completion of the first-floor column casting, commencement of formwork and reinforcement for the first-floor slab, and the start of masonry (brickwork) for the ground floor.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +12%
Completion Rate▲ +12%