25 Nov 2026
Main video
Engineering Report
Detected changes
Significant progress on the concrete structure; the roof of the completed area has been cast, and the first-floor columns are prepared, while carpentry and steel reinforcement works continue for the foundations in the remaining areas.
Progress reading
The overall completion rate has increased from 8% to 20% (+12%), which visually aligns with the transition from the foundation stage to the casting of the ground floor slab and the commencement of the first-floor columns.
vs previous visit
Compared to the previous visit, the site has transitioned from excavation and initial foundation work to a completed concrete roof structure, with a noticeable increase in labor and equipment (concrete pumps) on-site.
Expected next milestones
Completion of the first-floor column casting, commencement of formwork and reinforcement for the first-floor slab, and the start of masonry (brickwork) for the ground floor.