12 Apr 2026
Main video
Engineering Report
Detected changes
Execution of excavation and earthworks, with accumulation of excavated soil piles
Installation of temporary fencing to define the work zone
Delivery of concrete block stacks and mobilization of site caravans
Presence of heavy equipment (Hitachi excavator, Shantui excavator, bulldozer, and transport truck)
Progress reading
Visual observations are consistent with the initial baseline phase. Although the recorded overall completion rate is 0%, physical work on-site has effectively begun through leveling and excavation, which are the essential preliminary steps before commencing foundation and footing works.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of excavation work to the required level, pouring of blinding concrete, and commencement of reinforcement and formwork for the foundations.