Sadana Elemental
12 Apr 2026

12 Apr 2026

5%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Construction site work has commenced for the Sadana Elemental project, with current activities focusing on site preparation, preliminary excavation, and soil leveling. Heavy machinery, including excavators, bulldozers, and transport trucks, has been observed on-site, along with the delivery of concrete block supplies.
Detected changes
Entire site area100%

Execution of excavation and earthworks, with accumulation of excavated soil piles

Site perimeter95%

Installation of temporary fencing to define the work zone

Storage area100%

Delivery of concrete block stacks and mobilization of site caravans

Operations area90%

Presence of heavy equipment (Hitachi excavator, Shantui excavator, bulldozer, and transport truck)

Progress reading

Visual observations are consistent with the initial baseline phase. Although the recorded overall completion rate is 0%, physical work on-site has effectively begun through leveling and excavation, which are the essential preliminary steps before commencing foundation and footing works.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of excavation work to the required level, pouring of blinding concrete, and commencement of reinforcement and formwork for the foundations.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%