35%Overall▲ +17% · vs previous visit

Main video

Engineering Report

The casting of the current typical floor slab has been completed, while masonry works continue on the lower floors alongside internal mechanical and electrical service installations.
Detected changes
Concrete Structure100%

The upper roof slab has been cast, and reinforcement steel for the columns of the upcoming floors is now visible.

Masonry Works90%

Brick partition construction continues on the typical floors, with layout markings applied to the columns.

MEP Services90%

Installation of sewage and electrical conduits has commenced within the newly constructed partitions.

Progress reading

The completion rate remains steady at 18%, indicating that current efforts are focused on structural and internal service works, which do not significantly increase the overall completion percentage at this stage.

vs previous visit

Compared to the previous visit, progress has shifted from the concrete structure of the lower floors to the casting of a new floor slab, with notable advancements in masonry and internal utility works.

Expected next milestones

Completion of the next floor's column casting, continuation of masonry works, and commencement of internal plastering.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +17%
Completion Rate▲ +17%
0%