18 Oct 2026
Main video
Engineering Report
Detected changes
The upper roof slab has been cast, and reinforcement steel for the columns of the upcoming floors is now visible.
Brick partition construction continues on the typical floors, with layout markings applied to the columns.
Installation of sewage and electrical conduits has commenced within the newly constructed partitions.
Progress reading
The completion rate remains steady at 18%, indicating that current efforts are focused on structural and internal service works, which do not significantly increase the overall completion percentage at this stage.
vs previous visit
Compared to the previous visit, progress has shifted from the concrete structure of the lower floors to the casting of a new floor slab, with notable advancements in masonry and internal utility works.
Expected next milestones
Completion of the next floor's column casting, continuation of masonry works, and commencement of internal plastering.