51%Overall▲ +16% · vs previous visit
Main video
Engineering Report
The project has seen significant progress in its concrete structure, with the casting of the top-floor slab now complete. Brickwork is ongoing on the lower levels, and the site is being prepared for interior finishing works.
Detected changes
Concrete Structure
Completion of the top-floor slab casting using on-site concrete pumps.
Masonry Works
Ongoing brickwork on typical floors, with interior plastering works now visible in select units.
Progress reading
The completion rate has increased by 16% to reach 51%, which visually aligns with the casting of the top-floor slab and the intensification of brickwork on the lower levels compared to the previous site visit.
vs previous visit
Compared to the previous visit, construction has progressed from the mid-level floors to the completion of the top-floor concrete structure, with a noticeable increase in brickwork infill.
Expected next milestones
Commencement of roof waterproofing works and intensification of MEP (mechanical, electrical, and plumbing) installations within the completed floors.
Progress
0%OverallAverage item progress
0/1 completeavg ▲ +16%
Completion Rate▲ +16%
0%
35% → 51%+16%vs previous visit