22 Jul 2026
Main video
Engineering Report
Detected changes
Significant progress in roof tiling and installation of upper water tanks, with the completion of waterproofing and thermal insulation in service areas.
Completion of most exterior painting and metalwork, with some scaffolding remaining in limited sections for final touches.
Execution of plastering, primary painting, and aluminum window installation, along with the commencement of sanitary ware and lighting fixture installations in select units.
Ongoing paving and flooring coordination in the courtyard, including the preparation of planter boxes and walkways.
Progress reading
The 2% increase reflects the shift in operational focus from structure and facades to meticulous interior finishing, site landscaping, and roofing. This phase requires high precision and typically takes more time compared to major structural construction works.
vs previous visit
Compared to the previous visit, there is clear progress in roof tiling and the landscaping of the internal courtyard, which was previously in the foundation stages; additionally, most external openings have been sealed with aluminum windows.
Expected next milestones
Complete removal of external scaffolding, completion of external lighting works, and testing of internal HVAC and fire systems.