Grand Sadana - Hotel
22 Jul 2026

22 Jul 2026

91%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The Grand Sadana Hotel project has reached advanced stages of final finishing, with a completion rate of 91%. Current work is focused on completing roof cladding, landscaping the internal courtyard, and finalizing interior finishes for the units, while exterior facade work continues in its final stages.
Detected changes
Roofing and Insulation95%

Significant progress in roof tiling and installation of upper water tanks, with the completion of waterproofing and thermal insulation in service areas.

Exterior Facades90%

Completion of most exterior painting and metalwork, with some scaffolding remaining in limited sections for final touches.

Interior Finishes85%

Execution of plastering, primary painting, and aluminum window installation, along with the commencement of sanitary ware and lighting fixture installations in select units.

Courtyard and Site Works90%

Ongoing paving and flooring coordination in the courtyard, including the preparation of planter boxes and walkways.

Progress reading

The 2% increase reflects the shift in operational focus from structure and facades to meticulous interior finishing, site landscaping, and roofing. This phase requires high precision and typically takes more time compared to major structural construction works.

vs previous visit

Compared to the previous visit, there is clear progress in roof tiling and the landscaping of the internal courtyard, which was previously in the foundation stages; additionally, most external openings have been sealed with aluminum windows.

Expected next milestones

Complete removal of external scaffolding, completion of external lighting works, and testing of internal HVAC and fire systems.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +2%
Completion Rate▲ +2%