Grand Sadana - Hotel
30 Aug 2025

30 Aug 2025

54%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The images show significant progress in the structural concrete works, with current efforts focused on reinforcing and pouring the slabs for the upper floors and preparing the columns. The site is witnessing intensive labor activity with concrete pumps present, alongside ongoing red brick masonry work for the lower floors.
Detected changes
Upper Ceilings95%

Completion of reinforcement steelwork for large areas of the upper ceiling, including plumbing and electrical installations.

Columns90%

Preparation and carpentry for column reinforcement steel for the next floor across several sectors.

Facades85%

Ongoing exterior wall masonry using red bricks across the typical floors.

الموقع العام95%

تواجد مكثف للعمالة ومعدات صب الخرسانة (مضخة خرسانية) في الموقع.

Progress reading

Although the recorded completion rate is 0%, the images confirm that the project has surpassed the foundation stage and reached the typical floors (approximately the fourth or fifth floor). This indicates that an update is required for the official completion data to reflect the actual progress on-site.

vs previous visit

Compared to the previous site visit photos, there is a noticeable increase in the area of poured slabs and progress in the formwork and reinforcement for the upper floors, in addition to a clear increase in the red brick masonry walls across the lower and middle floors.

Expected next milestones

Pouring the slabs currently under reinforcement, commencing internal plastering for floors where masonry is complete, and finalizing the concrete structure for the remaining floors.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +14%
Completion Rate▲ +14%