10 Jul 2025
Main video
Engineering Report
Detected changes
Completion of fourth-floor column casting and commencement of formwork and carpentry for the fifth-floor slab
Execution of external wall masonry using red bricks for the first, second, and third floors at varying stages of completion
Preparation and stockpiling of construction materials (bricks, timber) around the building perimeter with site safety fencing in place
Progress reading
The images show that the project has moved past the foundation and substructure stages and is currently in the upper concrete structure and masonry phase. Although the recorded completion rate is 0%, the visual evidence indicates actual progress in the structure and masonry that requires an update to the official data.
vs previous visit
No previous visit available for comparison
Expected next milestones
Pouring the current floor slab, completing masonry work for the upper floors, and commencing initial electrical and plumbing installations.