Grand Sadana - Hotel
10 Jul 2025

10 Jul 2025

40%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Significant progress has been observed in the construction works of the Grand Sadana project, with the concrete structure reaching the fifth floor in parts of the building. Current works are focused on the reinforcement and formwork of the roof slab for the last visible floor, while red brick masonry continues for the lower typical floors.
Detected changes
Structural Framework95%

Completion of fourth-floor column casting and commencement of formwork and carpentry for the fifth-floor slab

Masonry Works90%

Execution of external wall masonry using red bricks for the first, second, and third floors at varying stages of completion

General Site85%

Preparation and stockpiling of construction materials (bricks, timber) around the building perimeter with site safety fencing in place

Progress reading

The images show that the project has moved past the foundation and substructure stages and is currently in the upper concrete structure and masonry phase. Although the recorded completion rate is 0%, the visual evidence indicates actual progress in the structure and masonry that requires an update to the official data.

vs previous visit

No previous visit available for comparison

Expected next milestones

Pouring the current floor slab, completing masonry work for the upper floors, and commencing initial electrical and plumbing installations.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%