25 Jun 2026

25 Jun 2026

29%Overall▲ +9% · vs previous visit

Main video

Engineering Report

The project shows significant progress in the structural concrete works, with the roof slab casting completed for one of the upper floors and the commencement of formwork and reinforcement for the columns and concrete walls of the following floor. The site is witnessing intensive activity with the presence of casting equipment and labor at various work points.
Detected changes
Roof slab (top level)100%

Concrete pouring completed, partial removal of formwork, and commencement of preparations for rising columns

Columns and shear walls95%

Installation of reinforcement steel and formwork for columns on the new floor

Site perimeter90%

Organization of building materials (red bricks) on the edges of the cast slabs in preparation for masonry work

Progress reading

Although the completion rate recorded in the data is 0%, the images clearly show that the project has surpassed the foundation stage and reached the typical floors (approximately the third or fourth floor above ground). The visible changes indicate a good pace of work on the structural frame.

vs previous visit

Compared to the photos from the previous visit, we observe the work progressing from the slab pouring stage (where the concrete pump was active) to the vertical preparation stage for the columns. In the previous photos, the wooden formwork for the ceiling covered a larger area, while the current photos show the ceiling poured and ready for the subsequent works.

Expected next milestones

Pouring the columns and walls of the current floor, commencing the wooden formwork for the next ceiling, and starting the external masonry (block) works.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +9%
Completion Rate▲ +9%