Sadana Loftec
24 Jan 2026

24 Jan 2026

12%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Concrete pouring for the project's raft foundation has commenced. The images show the simultaneous use of three mobile concrete pumps to ensure continuous pouring, alongside a heavy presence of concrete mixer trucks on-site. Excavation, shoring, blinding layer placement, and foundation reinforcement have been completed in the active section of the site.
Detected changes
Foundation Area100%

Pouring reinforced concrete for the raft foundation and covering a significant portion of the reinforcement steel with concrete

Site Perimeter95%

Presence of 3 concrete pumps (2 blue and 1 yellow) and more than 6 concrete mixer trucks

Excavation Works90%

Appearance of an adjacent excavation area still in the earth leveling stage with excavation equipment (excavator) present

Shoring85%

Installation of the shoring system for excavation sides and preparation of wooden formwork surrounding the foundations

Progress reading

Although the recorded overall completion rate is 0%, the photos confirm that the preparation phase has been surpassed and major structural works (foundations) have begun. Work is currently underway on pouring the raft foundation, a critical stage that represents the actual launch of the concrete structure.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of the raft foundation pouring, commencement of reinforcement and pouring for basement/ground floor columns, and foundation waterproofing.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%