24 Jan 2026
Main video
Engineering Report
Detected changes
Pouring reinforced concrete for the raft foundation and covering a significant portion of the reinforcement steel with concrete
Presence of 3 concrete pumps (2 blue and 1 yellow) and more than 6 concrete mixer trucks
Appearance of an adjacent excavation area still in the earth leveling stage with excavation equipment (excavator) present
Installation of the shoring system for excavation sides and preparation of wooden formwork surrounding the foundations
Progress reading
Although the recorded overall completion rate is 0%, the photos confirm that the preparation phase has been surpassed and major structural works (foundations) have begun. Work is currently underway on pouring the raft foundation, a critical stage that represents the actual launch of the concrete structure.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the raft foundation pouring, commencement of reinforcement and pouring for basement/ground floor columns, and foundation waterproofing.