12 Apr 2026
Main video
Engineering Report
Detected changes
Completion of the entire concrete raft foundation pouring and commencement of vertical columns and walls
Installation of wooden formwork (carpentry) and reinforcement steel for a large number of concrete columns and walls
Continued presence of a mobile concrete pump and transit mixers to execute ongoing pouring works
Progress reading
The images demonstrate a qualitative shift from sub-surface foundation works to the commencement of the vertical structure. The density of wooden formwork distributed across the entire area indicates an accelerated pace of work to prepare the vertical structural elements for pouring.
vs previous visit
During the previous visit (2026-01-24), the site was in the stage of pouring the reinforced concrete raft foundation, with an intensive presence of pumps for the floor casting. In the current visit, the floor has been fully completed, and the initial signs of the first floor have emerged through the wooden formwork for the columns and walls.
Expected next milestones
Casting the vertical elements (columns and walls), followed by the commencement of carpentry and reinforcement work for the current floor slab.