Sadana Loftec
12 Apr 2026

12 Apr 2026

20%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The site has witnessed significant progress in construction activities, transitioning from the raft foundation pouring stage observed in the previous visit to an advanced stage of the above-ground concrete structure. Work is currently underway on the formwork and reinforcement for the basement/ground floor columns and walls, with concrete pumps actively operating on-site.
Detected changes
Entire project footprint100%

Completion of the entire concrete raft foundation pouring and commencement of vertical columns and walls

Columns and walls95%

Installation of wooden formwork (carpentry) and reinforcement steel for a large number of concrete columns and walls

Equipment100%

Continued presence of a mobile concrete pump and transit mixers to execute ongoing pouring works

Progress reading

The images demonstrate a qualitative shift from sub-surface foundation works to the commencement of the vertical structure. The density of wooden formwork distributed across the entire area indicates an accelerated pace of work to prepare the vertical structural elements for pouring.

vs previous visit

During the previous visit (2026-01-24), the site was in the stage of pouring the reinforced concrete raft foundation, with an intensive presence of pumps for the floor casting. In the current visit, the floor has been fully completed, and the initial signs of the first floor have emerged through the wooden formwork for the columns and walls.

Expected next milestones

Casting the vertical elements (columns and walls), followed by the commencement of carpentry and reinforcement work for the current floor slab.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +8%
Completion Rate▲ +8%
0%

Drone Photography

On-site Photography

3D Rendering

ShareChat on WhatsApp