Sadana Loftique
12 Nov 2026

12 Nov 2026

68%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The project has seen significant progress in concrete structure and masonry works, with interior finishing works commencing in select units. The roof slab of the main building has been cast, brickwork continues on the typical floors, and mechanical and electrical installations are underway.
Detected changes
Concrete Structure

The roof slab of the main building's top floor has been poured, with finishing works for the rooftops currently underway.

Masonry Works

Brickwork continues on the facades and typical floors, with visible progress in room partitioning.

Interior Finishes

Plastering works have commenced in select rooms, ceramic tiling is being installed in bathrooms, and air conditioning ducting is being laid.

Progress reading

The images reflect an 8% increase in overall completion, as work has transitioned from the concrete structure of the middle floors to the completion of the top floor roof and the start of intensive interior finishing works.

vs previous visit

Compared to the previous visit, the casting of the upper floors has been fully completed, and the interior finishes are now clearly visible, whereas the previous visit focused primarily on the concrete structure and exterior masonry.

Expected next milestones

Completion of plastering and interior finishing works, commencement of exterior facade installation, and extension of electromechanical services on the remaining floors.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +8%
Completion Rate▲ +8%
0%

Drone Footage

On-site Photography

360° View

3D Model

ShareChat on WhatsApp