12 Nov 2026
Main video
Engineering Report
Detected changes
The roof slab of the main building's top floor has been poured, with finishing works for the rooftops currently underway.
Brickwork continues on the facades and typical floors, with visible progress in room partitioning.
Plastering works have commenced in select rooms, ceramic tiling is being installed in bathrooms, and air conditioning ducting is being laid.
Progress reading
The images reflect an 8% increase in overall completion, as work has transitioned from the concrete structure of the middle floors to the completion of the top floor roof and the start of intensive interior finishing works.
vs previous visit
Compared to the previous visit, the casting of the upper floors has been fully completed, and the interior finishes are now clearly visible, whereas the previous visit focused primarily on the concrete structure and exterior masonry.
Expected next milestones
Completion of plastering and interior finishing works, commencement of exterior facade installation, and extension of electromechanical services on the remaining floors.