Vida
1 Jul 2026

1 Jul 2026

18%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The concrete pouring for the ground floor (or mezzanine) roof slab has been completed across the entire project area, with preparations and formwork underway for the columns and concrete walls of the next floor. The site is currently transitioning from ground-level structural works to the typical floors.
Detected changes
Concrete Structure100%

Full casting of the concrete slab for the current level is complete, with reinforcement rebar for columns and shear walls protruding in preparation for the next phase.

Carpentry and Shoring Works95%

Wooden formwork and metal shoring remain in place beneath the newly cast slab, with carpentry work commencing for the rising columns.

Electromechanical Installations90%

Plumbing and supply sleeves are visible penetrating the concrete slab at the locations of shafts and bathrooms.

General Site100%

The site is well-organized with the perimeter fence (Fayda) completed, and the storage area remains confined due to the nature of the surrounding area.

Progress reading

Although the reported completion rate remains steady at 10%, the photos show tangible progress in finishing the slab pouring for the current floor compared to the previous visit's photos, which only showed formwork and reinforcement works.

vs previous visit

The fundamental difference is the transition from the 'formwork and reinforcement' phase (as seen in photos 20-25) to the 'casting completion' phase (as seen in photos 1-5). The concrete pump present during the previous visit has been dismantled following the completion of the main casting works for the current level.

Expected next milestones

Commencement of casting the first-floor columns, followed by the carpentry and reinforcement works for the first-floor ceiling.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +8%
Completion Rate▲ +8%