Townhouse
29 Jan 2026

29 Jan 2026

35%Overall▲ +15% · vs previous visit

Engineering Report

Significant progress has been achieved on the project with an additional 15% completion rate, as work transitioned from the foundation and ground beam stage to the concrete structure of the typical floors. The completion of the ground floor columns and upper floor ceiling slabs is clearly visible across the two main building blocks, with ongoing carpentry and steelwork and concrete pumps present on-site.
Detected changes
Structural Framework100%

Completion of concrete pouring for typical floor slabs and commencement of column works for the next level

Masonry Works95%

Commencement of delivery and stockpiling of red bricks on the cast floors in preparation for wall construction

General Site90%

Removal of wooden formwork from significant portions of the structure, revealing the layout of the residential units

Progress reading

The increase in completion rate from 20% to 35% reflects the actual transition from underground works (foundations) to the superstructure's concrete works. Current images show the completion of at least two slabs above ground level, justifying the jump in the percentage.

vs previous visit

During the previous visit, work was focused exclusively on the steel reinforcement and formwork for the ground beams and foundation pouring. In contrast, current photos show clear vertical growth of the buildings, with the concrete structure completed for several floors and a heavy presence of pouring equipment (pumps and mixers) to complete the remaining slabs.

Expected next milestones

Completion of the roof annex pouring, commencement of masonry work (walls), and the start of preliminary electrical and plumbing installations within the structural frame.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +15%
Completion Rate▲ +15%
0%