Townhouse
29 Jan 2026

29 Jan 2026

60%Overall▲ +25% · vs previous visit

Engineering Report

Significant progress has been achieved in the townhouse project, moving from the concrete slab casting phase to an advanced stage that includes the completion of the structural framework, the commencement of blockwork, and the preparation of upper roofs, bringing the overall completion rate to 60%.
Detected changes
Structural Frame95%

Completion of concrete pouring for typical floor slabs and removal of most wooden formwork in the first building

Masonry Works90%

Commencement of cement block masonry on the ground and first floors for unit partitioning

General Site100%

Presence of a concrete pump and mixing trucks on-site to complete pouring works in the adjacent building

Ceilings and Slabs85%

Preparation of reinforcement steel and formwork for the penthouse slabs in parts of the project

Progress reading

The 25% increase in the completion rate is visually evident in the transition from the initial structural skeleton (newly cast slabs) to the architectural partitioning phase using blockwork, while casting works continue on the project's annex buildings.

vs previous visit

Compared to previous images, it is noted that the ceilings that were under wooden formwork have been poured and the formwork removed. Additionally, the walls of the residential units have clearly begun to appear using masonry, whereas previous images showed only the concrete structure.

Expected next milestones

Completion of masonry work (blockwork) for all floors, commencement of initial electrical and plumbing installations, and the start of internal plastering works.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +25%
Completion Rate▲ +25%