25 Jun 2026
Main video
Engineering Report
Detected changes
Completion of plastering and initial white painting works, with significant removal of scaffolding
Execution of waterproofing layers (bituminous membranes) and preparation of AC and service openings
Clearing the site of heavy construction debris and commencing the shaping of entrances and interconnecting pathways
Installation of metal pergolas on select upper balconies and preparation of arched window openings
Progress reading
The images reflect a substantial leap from 35% to 85% completion. The site has transitioned from the structural framing stage (slabs and columns) seen in the previous visit to advanced finishing stages, accounting for the 50% progress achieved.
vs previous visit
During the previous visit, carpentry and blacksmithing for ceiling casting were underway with concrete pumps on-site. Current photos show buildings with complete architectural features, following the conclusion of masonry and external plastering, and the commencement of insulation works.
Expected next milestones
Installation of windows and doors, completion of final painting works, commencement of flooring installation, and external paving works.