Townhouse
25 Jun 2026

25 Jun 2026

85%Overall▲ +25% · vs previous visit

Main video

Engineering Report

The project has shown significant progress with an overall completion rate of 85%. The concrete structure is fully finished, and external plastering (rendering) has been completed for most facades. Additionally, roof waterproofing works and the installation of metal frames for some canopies have commenced.
Detected changes
Exterior Facades100%

Completion of plastering and initial white painting works, with significant removal of scaffolding

Rooftops95%

Execution of waterproofing layers (bituminous membranes) and preparation of AC and service openings

General Site90%

Clearing the site of heavy construction debris and commencing the shaping of entrances and interconnecting pathways

Balconies and Openings100%

Installation of metal pergolas on select upper balconies and preparation of arched window openings

Progress reading

The images reflect a substantial leap from 35% to 85% completion. The site has transitioned from the structural framing stage (slabs and columns) seen in the previous visit to advanced finishing stages, accounting for the 50% progress achieved.

vs previous visit

During the previous visit, carpentry and blacksmithing for ceiling casting were underway with concrete pumps on-site. Current photos show buildings with complete architectural features, following the conclusion of masonry and external plastering, and the commencement of insulation works.

Expected next milestones

Installation of windows and doors, completion of final painting works, commencement of flooring installation, and external paving works.