3 Aug 2025
Engineering Report
Detected changes
Commencement of reinforced concrete pouring using a mechanical pump with labor present for surface finishing
Completion of reinforcement steelwork and formwork, ready for concrete pouring
Organizing soil stockpiles in the center of the site and preparing access tracks for equipment movement
وجود تشوينات ترابية ناتجة عن أعمال الحفر والتسوية
Progress reading
The visible completion rate (20%) aligns with the conclusion of the excavation and backfilling phases and the actual start of the substructure concrete pouring. The completion of formwork and steel reinforcement for most footings indicates steady progress in this critical stage.
vs previous visit
No previous visit for comparison
Expected next milestones
Completion of all ground beam casting, commencement of waterproofing for footings, followed by the start of column necks and backfilling between footings.