23 Oct 2025
Engineering Report
Detected changes
Completion of pouring the lower floors and commencement of reinforcement steel and formwork for the current floor slab, with a high density of labor observed preparing the upper reinforcement network.
Commencement of cement brick wall construction on floors where concrete formwork has been removed, accounting for the 10% progress in finishing works.
Organization of the storage area and a heavy presence of construction materials (reinforcement steel) around the building perimeter, alongside ongoing reinforced formwork.
Progress reading
The photographs align with the surge in concrete works from 10% to 40%, as the project transitioned from ground level (raft foundation) to the construction of the vertical structure and slabs. The images also confirm the start of preliminary finishing works (masonry).
vs previous visit
The visual difference is significant; previous visit photos (21-26) showed only the reinforcement stage of the foundation raft, whereas current photos (1-20) show the completion of several levels of the concrete structure and the commencement of masonry work.
Expected next milestones
Completion of the remaining slab pouring, commencement of initial plumbing and electrical rough-ins within the walls, and intensification of masonry work.