Sadana Boutique
21 May 2026

21 May 2026

75%Overall▲ +24% · vs previous visit

Main video

Engineering Report

The project has shown significant progress in external finishing and facade works. Most of the stone and glass panels for the main facades have been installed, and the metal scaffolding that covered the building during the previous visit has been removed. Additionally, landscaping work has commenced in the front courtyard.
Detected changes
Exterior Facades100%

Complete removal of metal scaffolding and installation of stone cladding, glazing, and upper cornices

Roof95%

Installation of water tanks and mechanical system extensions on the final roof level

General Site (Ground Level)90%

Commencement of ground leveling and infrastructure preparation for entrances and parking areas

Windows and Balconies100%

Installation of protective railings for balconies and fixing of glass frames

Progress reading

Although the recorded completion rate is 0%, the photos clearly show the project's transition from the structural and initial finishing stages (seen in the previous visit) to advanced final finishing stages for the facades and roof. This indicates an expected update to the actual completion percentages soon.

vs previous visit

Compared to the visit on 2026-02-19, we observe the removal of the scaffolding that previously surrounded the entire building. The exterior wall painting and cladding are now complete, and the HVAC systems and rooftop tanks have been installed. In contrast, the previous visit showed the building in the external plastering and insulation installation phase.

Expected next milestones

Completion of external paving and lighting, commencement of final interior finishing works, and installation of the main gates.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +24%
Completion Rate▲ +24%
0%