20 Oct 2025
Main video
Engineering Report
Detected changes
Completion of concrete pouring for all floors up to the upper annex and roof rooms
Completion of a significant portion of internal and external wall construction, with architectural openings clearly visible
Installation of metal scaffolding around the entire building perimeter and commencement of splashing and plastering works in several sections
Installation of a stone sample and a window frame on the first floor of the main facade
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates that a substantial portion of the structural phase has been completed and the finishing stage has commenced. The building is structurally complete as a single unit.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of external plastering works, commencement of internal electrical and mechanical installations, and installation of windows and doors.