Sadana (2) Complex
20 Oct 2025

20 Oct 2025

63%Overall▲ +20% · vs previous visit

Main video

Engineering Report

The structural framework of the building (shell and core) has been fully completed, with significant progress in masonry work (blockwork) across all floors. External facades are entirely covered with metal scaffolding in preparation for plastering and exterior finishing works. Initial samples of window frames and stone ornaments have also been installed on limited sections of the front facade.
Detected changes
Structural Framework100%

Completion of concrete pouring for all floors up to the upper annex and roof rooms

Masonry Works (Blockwork)95%

Completion of a significant portion of internal and external wall construction, with architectural openings clearly visible

Exterior Facades90%

Installation of metal scaffolding around the entire building perimeter and commencement of splashing and plastering works in several sections

External Finishes85%

Installation of a stone sample and a window frame on the first floor of the main facade

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates that a substantial portion of the structural phase has been completed and the finishing stage has commenced. The building is structurally complete as a single unit.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of external plastering works, commencement of internal electrical and mechanical installations, and installation of windows and doors.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +20%
Completion Rate▲ +20%
0%

Drone Photography

360 Video

On-site Photography

3D Rendering