Grand Sadana - Hotel
14 Dec 2025

14 Dec 2025

69%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The report shows significant progress in the structural concrete and masonry work. Pouring of the typical floor slabs has been completed, and formwork and reinforcement for the upper floors have commenced, while external red brick masonry continues on the lower and middle floors.
Detected changes
Concrete Structure - Upper Roof95%

Completion of formwork and reinforcement for large areas of the final visible roof, with a concrete pump present on-site.

Masonry Works (Walls)90%

Increase in the level of red brick masonry work to include additional floors compared to the previous visit.

Site Perimeter85%

Increase in material and equipment stockpiles, with excavation and preparation works appearing in the plot adjacent to the main building.

Progress reading

Although the recorded completion rate is 0%, the photos reflect a different reality; the structural frame is in advanced stages (typical floors) and the masonry work has surpassed the halfway point of the building's total height.

vs previous visit

Compared to the October 2025 images, we observe progress in the pouring of at least one additional floor, a significant increase in the area of red-brick wall construction, and the relocation of cranes and equipment to handle the higher levels.

Expected next milestones

Completion of the current roof slab pouring, continuation of masonry work for the upper floors, and the commencement of MEP (mechanical, electrical, and plumbing) rough-ins within the structurally completed levels.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +4%
Completion Rate▲ +4%
0%

Drone Photography

360 Video

On-site Photography

3D Rendering