21 May 2026
Main video
Engineering Report
Detected changes
Completion of the installation and distribution of white plastic water tanks in designated areas.
Progress in tiling works (Interlock/Tiles) featuring circular and curved geometric patterns.
Continuation of exterior painting in brown and beige tones with workers present on scaffolding.
Execution of slope concrete pouring and waterproofing works in specific corners.
Progress reading
Although the recorded completion rate is 0%, the images reflect a different reality where the structural framework is nearing total completion with substantial progress in final finishing stages (roof and facades). This indicates a discrepancy between the entered data and the visual evidence.
vs previous visit
Compared to the previous visit, an increase in the number of roof-mounted water tanks is observed, along with clear progress in the tiling of upper walkways. Current images show better organization of construction materials in rooftop work areas compared to previous photos, which showed initial insulation works.
Expected next milestones
Removal of external scaffolding following the completion of facade painting, completion of mechanical connections for the tanks, and commencement of site landscaping surrounding the building.