Grand Sadana - Hotel
21 May 2026

21 May 2026

89%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The images show significant progress in the exterior finishing and roofing works for the Grand Sadana project. During this period, focus was placed on completing the installation of upper water tanks, insulation, and tiling in the roof areas, alongside the ongoing plastering and exterior painting of the facades, with scaffolding still in place across most of the building.
Detected changes
Building Rooftop95%

Completion of the installation and distribution of white plastic water tanks in designated areas.

Roof Flooring90%

Progress in tiling works (Interlock/Tiles) featuring circular and curved geometric patterns.

Exterior Facades85%

Continuation of exterior painting in brown and beige tones with workers present on scaffolding.

Open Roof Areas80%

Execution of slope concrete pouring and waterproofing works in specific corners.

Progress reading

Although the recorded completion rate is 0%, the images reflect a different reality where the structural framework is nearing total completion with substantial progress in final finishing stages (roof and facades). This indicates a discrepancy between the entered data and the visual evidence.

vs previous visit

Compared to the previous visit, an increase in the number of roof-mounted water tanks is observed, along with clear progress in the tiling of upper walkways. Current images show better organization of construction materials in rooftop work areas compared to previous photos, which showed initial insulation works.

Expected next milestones

Removal of external scaffolding following the completion of facade painting, completion of mechanical connections for the tanks, and commencement of site landscaping surrounding the building.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +8%
Completion Rate▲ +8%