Grand Sadana - Hotel
12 Apr 2026

12 Apr 2026

81%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The project shows significant progress in external finishing and facade work for the main building, while concrete structural work and masonry continue in the adjacent blocks. Most of the upper slabs for the hotel building have been poured, and the installation of rooftop mechanical systems has commenced.
Detected changes
Exterior Facades95%

Significant progress in exterior painting and cladding in white and gray, with scaffolding partially removed from completed sections.

Main Building Roof90%

Installation of air conditioning units, upper water tanks, and piping extensions.

Annex Buildings (Side Blocks)85%

Ongoing red brick partition work and pouring of final roof slabs for certain sections.

General Site80%

Partial cleaning of the building perimeter and commencement of entrance pathway preparation.

Progress reading

The images reflect the project's transition from the structural phase to the final facade finishing stage for the main building, while the lateral residential/hotel blocks remain in the advanced shell and core stages (masonry and slab pouring).

vs previous visit

Compared to the previous visit, we observe the completion of painting for large areas of the facades that previously appeared as raw concrete or plaster. Additionally, service systems have been installed on the roof, which were not present before.

Expected next milestones

Completion of external scaffolding removal, commencement of surrounding landscaping works, and completion of interior finishes and electromechanical installations.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +3%
Completion Rate▲ +3%