Intensive construction activity was observed at the Vida project site during the April 30, 2026 visit, with work currently focused on the building's concrete structure phase. The use of a central concrete pump for pouring structural elements is clearly visible, alongside a high density of labor performing formwork and shoring for columns and the site's surrounding retaining walls.
Detected changes
Retaining and Perimeter Walls95%

Completion of formwork and shoring for the perimeter walls and commencement of concrete pouring using the pump

Structural Columns90%

Preparation and installation of formwork for a large group of internal columns and shoring them in preparation for pouring

Site Flooring85%

Execution of cleaning works, preparation of reinforcement steel, and organized storage of timber materials in the work area

المعدات100%

تواجد مضخة خرسانة متحركة (Everdigm) في وضعية التشغيل لصب العناصر الإنشائية

Progress reading

Although the officially recorded completion rate is 0%, the photographs show tangible progress in the foundations, columns, and retaining walls. This indicates that the project is in the advanced stages of concrete structural work below ground level or on the ground floor.

vs previous visit

No previous visit available for comparison

Expected next milestones

Dismantling column formwork, commencing reinforcement and pouring of the current floor slab, and completing the waterproofing of retaining walls.

Progress

0%OverallAverage item progress
0/1 complete
Completion Ratenew
0%