30 Apr 2026
Main video
Engineering Report
Detected changes
Completion of formwork and shoring for the perimeter walls and commencement of concrete pouring using the pump
Preparation and installation of formwork for a large group of internal columns and shoring them in preparation for pouring
Execution of cleaning works, preparation of reinforcement steel, and organized storage of timber materials in the work area
تواجد مضخة خرسانة متحركة (Everdigm) في وضعية التشغيل لصب العناصر الإنشائية
Progress reading
Although the officially recorded completion rate is 0%, the photographs show tangible progress in the foundations, columns, and retaining walls. This indicates that the project is in the advanced stages of concrete structural work below ground level or on the ground floor.
vs previous visit
No previous visit available for comparison
Expected next milestones
Dismantling column formwork, commencing reinforcement and pouring of the current floor slab, and completing the waterproofing of retaining walls.