Grand Sadana - Hotel
18 Feb 2026

18 Feb 2026

78%Overall▲ +9% · vs previous visit

Main video

Engineering Report

The project has shown significant progress in exterior finishing and facade work, transitioning from the structural and exposed concrete phase to plastering, exterior painting, and the installation of scaffolding around the entire perimeter of the main building.
Detected changes
Exterior Facades95%

Completion of plastering works, commencement of exterior painting (white and gray), and removal of scaffolding from finished sections.

Rooftop90%

Completion of pouring upper parapets and roof rooms, and commencement of insulation and cleaning works.

External Perimeter85%

Clearing the site of major construction debris and beginning the leveling of areas surrounding the building.

المحيط الخارجي80%

إزالة بعض السقالات من الواجهات التي انتهت أعمال اللياسة بها، وتنظيم منطقة التشوين الأرضية.

Progress reading

Although the recorded completion rate in the data is 0%, the photos reflect a completely different reality. The project has reached advanced stages of exterior finishing (over 70% of the facades), indicating a discrepancy between the entered data and the visual progress.

vs previous visit

Compared to the previous visit, the building has progressed from a red brick concrete structure with tower cranes and concrete pumps to a structurally complete building. It is now largely covered with plaster and paint, and the main tower cranes have been dismantled.

Expected next milestones

Completion of exterior painting works, commencement of window and aluminum installation, and the start of final site landscaping.

Progress

0%OverallAverage item progress
0/1 completeavg ▲ +9%
Completion Rate▲ +9%
0%