18 Feb 2026
Main video
Engineering Report
Detected changes
Completion of plastering works, commencement of exterior painting (white and gray), and removal of scaffolding from finished sections.
Completion of pouring upper parapets and roof rooms, and commencement of insulation and cleaning works.
Clearing the site of major construction debris and beginning the leveling of areas surrounding the building.
إزالة بعض السقالات من الواجهات التي انتهت أعمال اللياسة بها، وتنظيم منطقة التشوين الأرضية.
Progress reading
Although the recorded completion rate in the data is 0%, the photos reflect a completely different reality. The project has reached advanced stages of exterior finishing (over 70% of the facades), indicating a discrepancy between the entered data and the visual progress.
vs previous visit
Compared to the previous visit, the building has progressed from a red brick concrete structure with tower cranes and concrete pumps to a structurally complete building. It is now largely covered with plaster and paint, and the main tower cranes have been dismantled.
Expected next milestones
Completion of exterior painting works, commencement of window and aluminum installation, and the start of final site landscaping.